$50,573,000= Original Total Cost for a New Build High School

-$ 2,580,000=Design Fees

____________________

$47, 993,000=Total Construction Cost

-$ 2,267,000=A reduction of 15,000 sq. ft. due to : ( 1) 5,000 sq.ft due to Central  Administration Offices moved out of new building and possibly to retained 1969 addition; (2) 10,000 sq. ft. reduction due to more compact design (likely three-story classroom area instead of a two story design) and better ratio of net to gross space). This reduction does not materially decrease the building's educational space.

 

$45,725,300

-$    500,000=Savings due to 1969 addition remaining intact

____________________

 

$45,225,300=New Construction Cost

$  2,580,000=Design Fees

____________________

$47,805,300=Total Cost of Project