
Northborough, Massachusetts
HIGH SCHOOL
BUILDING PROJECT FACT SHEET
High
School Building Project Fact Sheet
Space
and Facilities Needs at the High School
Enrollment at Algonquin is rising, and will soon exceed the school's
capacity of 1134-1193 students. Projected enrollments reach 1177 in academic year 2002/03, 1286 in 2003/04, and increase steadily thereafter, leveling off
at about 1600 students.
The high school is additionally in need of major renovation. The
original
building was opened in 1959, with a major addition in 1969. Although the
existing physical plant has been maintained, no substantial
infrastructure
upgrades have been made since the 1969 addition. Major systems such as
the
septic, mechanical, electrical, plumbing, fire safety, handicap access,
and
heating and ventilation are either past their expected lifetimes, or do
not
meet current code requirements.
Decisions by the Regional School Committee and by Voters
1996. Following town meeting approvals, the school committee contracted
with
the Office of Michael Rosenfeld to analyze the existing facility and to
guide the Feasibility Study Committee through an analysis of future facility
needs. A demographic study was commissioned.
1997. The school committee approved a preliminary plan for
renovation/addition.
1998. Response from the public indicated a strong interest in
consideration
of alternative solutions, including building a new school, as well as dissolving the regional school district. The Algonquin Building Planning Committee was formed. A second, more detailed demographic study was commissioned. An architectural firm, Keyes Associates, was engaged.
1999. In March, the Building Planning Committee recommended building a
single new high school. In June, following extensive public debate, the school
committee voted unanimously to bring the new build option forward to the
voters. The school committee additionally began negotiations with
MetLife
for the purchase of land adjacent to the existing high school.
2000. A purchase and sale agreement was executed between MetLife and the
Regional School District. In March and April, Northborough and
Southborough town meetings authorized this purchase. The town meetings additionally approved fees for the design of a new high school on land adjacent to
the existing high school, contingent upon debt exclusion ballot elections.
The debt exclusion measure passed in Southborough, but failed in
Northborough.
In September, simultaneous special town meetings accepted an amendment to
the Regional District Agreement, changing the formula by which capital costs
are allocated between the two towns. The Northborough special town meeting additionally approved design fees for a new high school under the new cost-sharing formula, contingent upon a debt exclusion election. The
debt exclusion subsequently failed at the ballot. (The design fee question
was
not reconsidered in Southborough, where the original vote was still valid).
In
October, following a series of special meetings with extensive public
input,
the school committee revised the new build plan, and voted to bring the
design fees question to a regional ballot election.
Split of Costs between Northborough and Southborough
Under the previous agreement, debt payments for capital costs were split
in
proportion to each town's share of enrollment in the year before the
capital
cost was incurred. The split remained constant throughout the 20-year
lifetime of the bonds, regardless of subsequent shifts in enrollment.
Under
the amendment of September 2000, payments will be split in proportion to
a
four-year rolling average of each town's share of enrollment. In
addition,
services contributed to the regional district by the towns will be
charged
to the district's operational budget, which previously did not account for
such
services. The operational budget has been, and will continue to be,
split in
proportion to each town's share of enrollment on October 1 of the
previous
fiscal year.
The Reimbursement Issue
The Massachusetts Department of Education, through its School Building
Assistance Program, pays most of the costs of building schools. Its
payment
formulas and requirements, including especially the need for SBA
approval of
projects, dominate the cost analysis of any school project considered by
the
Regional School Committee. Until the end of this year, the reimbursement
rate for the Northborough-Southborough Regional District is 65%. Starting in
2001, a new formula will determine the reimbursement rates. The Department of Education has not released sufficient information for anyone to
determine
what the regional district's new rate will be. To qualify for
reimbursement
at the old rate, a school project must have received approval from SBA
and
design fees must be approved by the voters, both by December 30, 2000;
and
the design must be completed and the whole project approved by the
voters by
June 30, 2001. The Department of Education has indicated that projects
"grandfathered" under the old formula will be considered
eligible for
reimbursement under the new formula, if the new formula results in a
higher
reimbursement rate.
The project presently before the voters is the only solution to the high
school capacity and facilities problem which stands a reasonable chance
of
qualifying for reimbursement under the old formula. Other solutions
could be
brought forward on time, in theory, but the rapid approach of the
deadline,
and the time scale on which meetings and votes can be held, would make
this
extremely difficult.
Solution Proposed by the Regional School Committee
The proposal is to build a new 290,720 square foot high school on land
adjacent to the existing high school, demolish the 1959 building, and
keep
the 1969 3-story addition. It differs from the previous plan, which
called
for the construction of a 305,000 square foot high school, and complete
demolition of the old high school. The change from 305,000 to 290,720
square
feet was made without reducing the educational specifications (number
and
size of classrooms, for example), by moving central administrative
offices
to the 1969 addition, and by adopting a maximally compact, 3-story design
for the new building. These changes reduce the estimated cost of the project
from $50.6 million to $47.8 million (including design fees).
Alternative Plans
The feasibility committee, the building planning committee, and the
school
committee have considered several alternative plans over the course of
4-5
years of study and deliberation. The most recent was a $30 million
addition/partial renovation plan generated by two Northborough
residents.
The school committee, advised by the architectural consultant that this plan
would not be eligible for state reimbursement (and thus would cost the
towns
far more than a state-reimbursable $50 million project), dropped it from
further consideration. The alternative plan with the greatest
feasibility
and public support was a thorough renovate/add project, which was deemed by
the building planning committee to be a viable, though not preferred,
option.
Tax Impact
The tax impact of the $47.8 million new-build project, including both
interest payments and state reimbursement at 65%, averaged over the
lifetime
of the bonds, is $137.81 per year for the average house in Northborough
(based on a value of $200,000), and $154.25 per year for the average
house
in Southborough (based on a value of $325,000).
Consequences of Different Outcomes of the Vote
A yes vote by a simple majority of regional voters authorizes the
Regional
School District to incur debt not to exceed $2.58 million, to pay fees
for
the design of a new high school. This vote would enable the school
committee
to hire an architectural firm, and meet the December 30 deadline for
reimbursement under the old formula.
In a regional vote, it is possible for the measure to pass with a
majority
of voters in one town voting against it. Although the school committee
would be
authorized by such a vote to commission a design, it would not be
obligated to do so, and would have to decide whether to proceed under the
circumstances.
A no vote would prevent the project from going forward. We would miss
the
deadline for reimbursement under the old formula. Because nearly
immediate
construction of a new high school is the only long-term plan which
solves
the space problem before the capacity of Algonquin is exceeded, it would be
necessary to purchase temporary or portable classroom space. Such
purchases
are not reimbursable by the state.
Times and Places of Voting
Saturday, November 18, 12:00 noon to 8:00 p.m., at the usual precinct
polling places.
Tony Poteete
November 2000
back
to ARHS Project page
home
|